Construction Permits, Codes & Inspections in FL: What You Need to Know

Last updated November 17, 2026

Kitchen remodelingKitchen remodeling
Bathroom remodelingBathroom remodeling
Home additions & ADUHome additions & ADU
RoofingRoofing
Windows & doorsWindows & doors
Driveway & paversDriveway & pavers
FenceFence
Every visit starts with

Free written scope consultation - allowances, timeline, and change-order rules on paper before a single trade is scheduled

We have financing partners for your dream remodel*On approved credit; ask us about your options
Get your free estimate

Construction Permits, Codes & Inspections in FL: What You Need to Know

A Miami homeowner once sat down at the closing table to sell a house she’d owned for nine years, only to find out the addition at the back of the property – the one the previous owner built – had never been permitted. No final inspection existed in county records. The buyer’s lender wouldn’t fund until it was sorted out. She had to escrow $40,000 and retroactively permit work the county had never seen, on a contractor who had long since vanished. The deal nearly died over a room she never built. The lesson stuck with us: in Florida, permits aren’t paperwork. They’re the legal history of your house, and whoever buys it next will read that history line by line.

Call (833) 968-1198

Quick Answer

Florida requires a building permit for almost any structural, electrical, plumbing, or mechanical work – additions, re-roofs, new fences over a set height, pools, and interior remodels that move walls or systems. Miami-Dade County adds strict High-Velocity Hurricane Zone (HVHZ) rules that exceed the statewide minimum, and inspections must pass at each phase before you move to the next. Skip a permit and you risk voided insurance coverage, a failed home sale, or forced demolition at your own cost.

Explore

Styles & brands we work with

  • Kitchen remodeling
  • Bathroom remodeling
  • Home additions & ADU
  • Roofing
  • Windows & doors
  • Driveway & pavers
  • Fence

Table of Contents

Which Projects Require a Permit in Miami-Dade?

This is the question that gets answered wrong most often, usually by a well-meaning neighbor. Here’s the straight version for Miami-Dade County. Any work that changes the structure, the building envelope, or the major systems of the home needs a permit. That includes additions, new windows and doors rated for the wind zone, re-roofs, and anything that touches mechanical, electrical, or plumbing.

The thresholds matter. A fence under 6 feet in most residential zones can go up without a permit, but cross that height and you’re in review. Sheds and accessory structures under 100 square feet are generally exempt; at or above that, permits apply. A pool shell and its electrical and barrier system always require permits, and they require inspections. Interior cosmetic work like paint, tile over an existing slab, or swapping a faucet usually doesn’t. Moving a plumbing fixture across the room does.

Miami’s specific triggers are ones homeowners underestimate. Impact windows and doors need permits because they’re load-path and product-approval items, and the county has to confirm the assemblies meet HVHZ product control. A wall removal, even a “non-bearing” one, needs a permit if you can’t document the framing; the county treats undocumented walls as structural until proven otherwise. In older neighborhoods like Little Havana, Coconut Grove, and parts of Coral Gables, a straightforward kitchen or bath remodel can trigger a compliance review because the underlying structures predate modern code – and inspectors will note what they see.

When in doubt, ask. Pulling a permit for work that turns out to be exempt costs a little time and a small fee. Skipping a permit that was actually required can cost five figures and stall a sale.

How the ePlan Portal Works and What Review Really Takes

Miami-Dade County runs its residential permitting through ePlan, the online submission and review system. You or your contractor create an account, upload plans, and track the submission through intake, review, and approval. Most routine residential submittals – re-roofs, fences, small structures – can move through ePlan without a paper trip to the county office. Larger projects, including additions and some remodels that require architecture or engineering, also go through ePlan but get a more thorough review.

Timelines vary widely by submission quality and type. A clean re-roof permit can move through in days to a couple of weeks. A home addition with a full plan set can take several weeks to a couple of months, depending on plan review workload and how many rounds of comments the reviewer issues. The single biggest variable isn’t the county – it’s how complete and accurate the plan set is on submission. A roof permit with a valid product approval number attached moves. A roof permit missing that number gets bounced to the back of the queue.

This is why third-party plan review matters. Florida allows qualified private providers to perform the plan review and inspection functions on many residential projects, which can shorten the front end of the process considerably. In our experience timing a Miami project, third-party review often shaves weeks off what a full county queue would take. A reputable contractor uses it on the right projects and county review on the others. It isn’t a shortcut around code; it’s a faster lane to the same standard.

What we tell every homeowner heading into permitting: expect a few review cycles even on a solid plan set. The first response from plan review is almost never “approved” on the first pass for anything more complex than a fence. Budget for two rounds of corrections on an addition and you won’t be disappointed.

The 2023 Florida Building Code and HVHZ: What Changed

The Florida Building Code updates every three years, and the 2023 edition carries changes that matter to residential work in Miami. Two stand out for homeowners: product approval documentation for weather-resistant envelopes got tighter, and wind-load requirements on roof-to-wall connections for additions and structural changes moved further into explicit engineering territory. Plans that used to pass with an engineer’s stamp and a product cut sheet now sometimes need a more detailed attachment narrative.

Here’s the part out-of-state contractors miss. Miami-Dade sits inside the High-Velocity Hurricane Zone, and HVHZ provisions don’t just meet the state code – they exceed it. Every product used in the building envelope has to be listed for HVHZ use with a valid Florida Product Approval or Miami-Dade Notice of Acceptance. That covers roofing underlayments, fasteners, impact glazing, and the connections tying the roof to the walls. A standard product that’s fine in Tampa isn’t automatically acceptable in Miami. The county checks the NOA number, not the brochure.

For additions, HVHZ plus 2023 code means engineering on the connection between the new addition and the existing house. Re-roofs mean the deck attachment method has to meet current uplift requirements, which sometimes means additional fastening even when the homeowner only wanted new shingles. A fence needs to be built for the wind zone too, which is part of why we use Ameristar steel and ActiveYards systems rated for the load. If a bid doesn’t mention HVHZ-compliance on the materials list, ask why – it’s the first thing the county will want to see.

The Inspection Sequence for Common Miami Projects

Inspections are where commitments get tested. An inspector arrives at specific milestones and either signs off or writes it up. Skip a phase and you can’t proceed to the next. Here’s the sequence for the four projects we handle most often in Miami residential construction.

Home Addition

  1. Site and foundation inspection after excavation and form work, before concrete pour.
  2. Foundation inspection once the slab or stem walls are placed.
  3. Framing inspection once walls are up, roof structure is in, and rough-ins are visible.
  4. Rough electrical, plumbing, and mechanical inspections before insulation.
  5. Insulation inspection with the walls open.
  6. Drywall and then gypsum inspection after final finishing.
  7. Final building, electrical, plumbing, and mechanical inspections at completion.

Re-Roof

  1. Pre-inspection of existing roof, often including a decking condition report.
  2. Underlayment and deck attachment inspection before any roofing material goes down.
  3. Final inspection after the cap sheet or shingles and all flashing are installed.

Fence

Most residential fence permits in Miami-Dade are single-inspection: the final. The inspector verifies the fence doesn’t encroach on the swale, meets height, and (where required by the association or the county) meets wind-load. We build with Jerith aluminum or Bufftech vinyl systems where the wind rating fits the site, which passes cleanly on the final.

Pool

  1. Pool shell excavation and steel inspection.
  2. Gunite or shell inspection once the structure is placed.
  3. Rough electrical and plumbing inspections for pumps, heaters, and conduit.
  4. Barrier inspection for the safety fence or enclosure.
  5. Final inspection after surface finish and water fill.

What a Failed Inspection Actually Requires

A failed inspection isn’t the end of a project – it’s a correction order. Here’s what actually happens, and why it’s not the crisis it feels like on the day.

The inspector issues a written correction list stating exactly what failed and what code section it references. Your contractor fixes those items and calls for a re-inspection. The re-inspection fee is real but small (typically well under $200 in Miami-Dade), and the timeline is usually a few days to a couple of weeks. A “partial” or “conditional” sign-off means the phase passed for the items that were complete, and the remaining items get inspected with a follow-up.

Common failures in Miami residential work are predictable: deck fastening that doesn’t match the HVHZ uplift table, missing product approval documentation for an impact window with no recorded NOA number, railing heights off by an inch on a pool barrier, or a framing inspection where an engineer’s letter is missing for a beam change. When we’re the contractor of record, none of these catch the county by surprise because we build to what the inspector will check. When we’ve been called in after a failed inspection on someone else’s job, the fix is almost always documentation first (get the right NOA, get the right engineer’s letter) and physical correction second.

The one failure that’s genuinely serious is a failure that reveals work was done without a permit in the first place. That becomes a retroactive permitting process, which is where the $40,000 escrow story lives. We’ve handled those in Miami; they’re slow, expensive, and sometimes require opening finished walls so the inspector can see what was actually built.

How Unpermitted Work Hits Your Insurance

Florida law gives insurers room to deny claims tied to unpermitted work, and they use it. If a storm damages an addition that was never permitted, the carrier can argue the work itself was out of compliance and limit or deny the portion of the claim that attaches to it. If a fire starts at an unpermitted electrical panel, the claim may be adjusted based on the code violation. Homeowners who buy a place with a “nice addition out back” often don’t learn this until the claim is filed.

Roofs are the clearest example. Florida insurers scrutinize the roof permit and the final inspection on a re-roof. A roof replaced after a storm without a permit may not qualify for the wind mitigation credit – and worse, may not be covered if it fails. On homes with newer construction or additions, carriers increasingly ask for the certificate of occupancy and permit history as part of underwriting. A missing permit can mean a non-renewal notice, not just a denied claim.

The takeaway for Miami owners: your insurance policy and your permit history are tied together whether you like it or not. Pulling the right permits and passing inspections isn’t just about the county – it’s the difference between a covered claim and a fight.

Permits and the Sale of Your Home

When a Miami home goes to market, the buyer’s title search and the permit history are reviewed. A missing permit doesn’t automatically kill a sale, but it forces the issue: the seller has to escrow funds, retroactively permit the work, or drop the price. In the current Miami market, a $40,000 escrow on a $900,000 sale is common where an unpermitted addition is discovered. The buyer’s lender won’t fund a non-permitted structure, and title insurance won’t clean it up without documentation.

The cleanest defense is a complete permit history with closed finals. If the home has had a kitchen remodel, an addition, a re-roof, or a pool installed, all of it should appear in ePlan with a matching final inspection. When you sell, your buyer’s agent and attorney will pull that history. The hours spent passing a framing inspection at the time of the build are the hours you save at closing.

Common Mistakes to Avoid

  • Trusting “it’s only cosmetic, no permit needed.” Swapping a load-bearing wall for a beam is never cosmetic. If a contractor says no permit is needed for any change to walls or systems, get a second opinion.
  • Letting a contractor pull the permit but never confirming it. In Miami, verify the permit in ePlan yourself before work starts. It’s free and takes about two minutes.
  • Assuming the roofer pulled the roof permit. Roofs are the most common un-permitted work we see in Miami after storm season. Ask for the permit number and check it.
  • Skipping the final inspection after a fence or pool install. A permit that’s never closed is treated like a permit that was never pulled when you sell.
  • Hiring a contractor with no Florida license or no insurance. Every contractor doing permitted work in Miami-Dade must be licensed and carry coverage. Ask for the license and verify it. If they can’t produce one, walk.
  • Ignoring HOA and city requirements on top of county permits. Coral Gables, Miami Beach, and Pinecrest each have their own review layers. A county permit doesn’t satisfy the city.
  • Letting a materials-cost-saving switch happen mid-build without re-documenting. A different shingle or window that isn’t HVHZ-listed can fail the final inspection after it’s already on the house.
Before & after

See the difference

Before - Recent ProjectBeforeAfter - Recent ProjectAfter
Recent Project
Before - Full RestorationBeforeAfter - Full RestorationAfter
Full Restoration
Before - Complete UpgradeBeforeAfter - Complete UpgradeAfter
Complete Upgrade

When to Call a Professional

There are projects where the permit process is genuinely a homeowner’s project – a single fence, a shed under the size threshold, a small repair. There are also projects where getting the permitting and inspection sequence wrong is expensive and hard to unwind. Home additions, structural changes, re-roofs, impact window replacement, pool installs, and any remodel that opens walls require a licensed contractor who manages ePlan, third-party review, and inspections as part of the job. If you’ve been handed a failed inspection on someone else’s work, we strongly recommend calling a licensed contractor rather than the same crew that failed it – the correction usually needs documentation the first crew didn’t produce. Groundwork Construction Co. of Miami offers free estimates in Miami – call (833) 968-1198. As Groundwork Construction Co. of Miami home outlines, we cover the full scope from permitting through final inspection, backed by the 730-Day Done Right Promise.

Frequently Asked Questions

The Bottom Line

Florida’s permitting system gets a bad reputation, but for Miami homeowners it’s the most reliable financial protection available on the biggest asset you own. Permits force documentation; inspections force verification; documentation protects your insurance claim and your resale. The projects that go wrong are almost always the ones where someone decided the permit was “probably not needed” – and the bill comes due at claim time or at closing, not at the time of the decision. Get the permit pulled, get it inspected, get it closed out with a final. And pick a contractor who treats that sequence as the job, not an afterthought. If you’re planning a permitted improvement in Miami, Groundwork Construction Co. of Miami will pull it, coordinate it, and stand behind it in writing. Whether you’re adding a room with Home Additions & ADU in Miami, installing new Driveway & Pavers in Miami, or a permitted fence, we handle the permits and the inspections from foundation to finish line, with live answers 24/7 – no voicemail, no waiting until Monday – and no-hassle upfront pricing on every estimate.

Call (833) 968-1198 for a free estimate. We’ll walk you through what your project actually needs in Miami-Dade, plus $1,000 off projects over $10,000 and 0% financing for 18 months on approved projects.

Written by the team at Groundwork Construction Co. of Miami.

Need Construction help in Miami? Licensed & insured · free written estimates
Call (833) 968-1198
Local Service Coverage

Request a Free Estimate in Miami

Tell us what you need - Groundwork Construction Co. of Miami responds fast. No obligation.

By submitting this form you agree to our Privacy Policy and consent to be contacted by phone, email or SMS about your request, including by local professionals who may handle it.

Call Now - 24/7 Dispatch