AfterHow long does a kitchen remodel take in Miami, FL?
A full kitchen remodel in Miami typically takes 12 to 20 weeks from the first design meeting to the final walkthrough, and that range is longer than the 6-to-12-week figure national guides quote. The difference is almost never the construction itself. It’s the Miami-Dade permit review, which can run three to six weeks before a single tool touches your kitchen, plus hurricane-season material delays and the structural surprises waiting inside older CBS homes once the walls open up. If you want a realistic date, Groundwork Construction Co. of Miami builds those variables into the schedule upfront. For a straight answer on your specific kitchen, call (833) 968-1198 and we’ll walk you through it.

Why Miami kitchens run longer than the timeline you read online
That 6-to-12-week number comes from parts of the country where permits move fast, the housing stock is wood-frame, and materials arrive on schedule year-round. Miami isn’t that place.
Miami-Dade County has some of the longest permit review windows in Florida, and kitchen work that touches electrical, plumbing, or structural walls needs a permit. The county operates its own product-approval system for wind-rated materials, which means the paperwork review is thorough. Thorough takes time. We submit early, follow the review closely, and flag corrections before they turn into a stalled week, but we can’t make the county move faster than it moves.
Then there’s the building itself. Much of Miami’s older housing stock is pre-1970s concrete block and CBS construction, with unreinforced masonry walls, flat or low-slope roofs, and plumbing and wiring that have been patched over several times. What’s behind the drywall is rarely a surprise we can see on the estimate. It’s what we find after demo.
A realistic Miami kitchen remodel timeline, phase by phase
Here’s how a 12-to-20-week schedule actually breaks down when we build one for a Miami home. A small kitchen remodel sometimes lands near the short end; a gut renovation with layout changes and structural work tends to run long.
| Phase | Typical duration | What drives it |
|---|---|---|
| Design and material selection | 2 to 4 weeks | Cabinet and countertop lead times, layout decisions |
| Permit submission and Miami-Dade review | 3 to 6 weeks | County review window, plan corrections |
| Material lead times (June through November) | Add 1 to 2 weeks | Hurricane-season shipping and delivery disruptions |
| Demo and rough-in | 1 to 2 weeks | What’s behind the walls once they open |
| Inspections | 3 to 5 business days each | Separate electrical and plumbing rough-in inspections |
| Finish work | 2 to 3 weeks | Cabinets, counters, tile, paint, fixtures |
Add it up and you’re looking at somewhere in that 12-to-20-week window under normal conditions. The phases overlap a little on a well-run job, but the permit review and the inspections don’t compress. They’re fixed. Plan around them.
Cost runs alongside that timeline, and a full kitchen remodel in Miami lands between $16,520 and $53,100 depending on size, layout changes, and the materials you choose. If you want the full price breakdown by scope, our Kitchen Remodeling in Miami page covers it line by line.
The Miami-Dade double-inspection reality that most guides skip
Before the walls close, your kitchen needs two separate county inspections: one for the electrical rough-in and one for the plumbing rough-in. They’re not bundled. Each one takes building department scheduling, usually three to five business days from when it’s requested, and each has to pass before the next phase can start.
Here’s where schedules quietly fall apart. An inspection gets flagged on a Thursday for something minor. The crew that was supposed to be there Monday needs to be rescheduled. The sub who was supposed to start Friday has to slide. If nobody’s answering the phone that Thursday night, that little flag turns into a lost week – and a lost week sometimes turns into two because now everyone downstream has to rebook.
We book inspection slots in advance as part of the schedule rather than reacting to them when they come up, and our calls are answered by a live person 24 hours a day, seven days a week. When something needs to move on a Thursday evening, we’re on it before Friday morning.
Opening walls in a pre-1970 Miami home: what we find
Once demo starts on a 1960s CBS kitchen, we regularly run into three things: unreinforced masonry that needs added support before new cabinets hang, deteriorated electrical conduit that has to be brought up to current code, and cast-iron drain lines that have rusted near the joints. Any one of these can add a week to the schedule while we assess, order, and install the fix.

That’s why we build a one-to-two-week contingency buffer into every kitchen quote as standard, not as an optional add-on. The alternative is a contractor who bids tight, hits the surprise, and either asks for a change order or drags the project out while everyone argues about it. We’d rather schedule the buffer and hand you back time if the walls are clean.
Groundwork’s technicians have up to 12 years of experience, and they’ve opened enough walls in this city to know which decades of construction tend to hide which problems. Our background-checked, uniformed technicians show up prepared for what’s likely behind the drywall instead of guessing.
Why the 730-Day Done Right Promise is really a timeline guarantee
Rushing a remodel is the fastest way to have to come back and do it again. A contractor with no real warranty has every incentive to close a job out on the calendar and move on – even if a cabinet gets hung slightly off, or a counter seam shows a little, or a tile corner doesn’t quite sit right.
Our 730-Day Done Right Promise means if something isn’t done right, we make it right – for two full years after the final walkthrough. That changes the math. We’re not trying to beat the schedule by a week and cut corners; we’re building it to last because a callback costs us more than a well-paced job. The timeline gets planned realistically, the work gets done to standard, and the promise backs it up in writing.
If you’re budgeting the project, it’s worth knowing the full range for the home improvement work you’re considering and how a kitchen remodel compares. Most full-kitchen projects land in the $16,520 to $53,100 range, with cabinet work alone typically between $4,720 and $15,340 and countertop installation between $2,360 and $7,670. We offer no-hassle upfront pricing, 0% financing for 18 months, and $1,000 off projects over $10,000, so the number you’re quoted is the number you pay.
FAQs
A kitchen remodel in Miami typically takes 12 to 20 weeks from the first design meeting to the final walkthrough. That’s longer than the national 6-to-12-week average because Miami-Dade permit review alone can take three to six weeks, and hurricane-season material delays and pre-1970 CBS construction surprises can add another week or two. Call (833) 968-1198 for a schedule built around your specific kitchen.
Permit review is the single biggest driver, followed by material lead times during hurricane season. Miami-Dade’s building department runs longer review windows than most of Florida, and construction materials ordered between June and November can sit in transit while a storm threat holds up shipping. Build one to two weeks of buffer into any schedule that crosses those months. A few minutes on the phone can confirm what your specific timeline looks like – call (833) 968-1198.
The contractor should handle the permit submission and the county review as part of the job. That’s one of the reasons the schedule starts earlier than most homeowners expect – the timeline begins at the design meeting, not at demo. We handle the paperwork, plan review, and inspection scheduling so you’re not chasing the county yourself. For an exact plan, call (833) 968-1198 for a free estimate and design consult.
Yes, a smaller scope runs considerably less – a small kitchen remodel in Miami typically lands between $10,620 and $23,600 compared with $16,520 to $53,100 for a full renovation. The smaller scope also shortens the timeline, since less demo, fewer inspections, and fewer material orders can pull the schedule closer to the 8-to-12-week range. If you’re deciding between the two, call (833) 968-1198 and we’ll walk through what your kitchen actually needs – estimates are free.
If you’d rather have your kitchen assessed in person than guess at the timeline, Groundwork Construction Co. of Miami offers a no-pressure design consult and free estimate. We’ll look at your kitchen, check what’s behind the walls, and give you a real schedule with the Miami-Dade permit window built in. Call (833) 968-1198.